Pri #
Proj #
Project Name Total Proj Cost SPLOST Cost
Details
Pri #
1
3.12
Brooker Ext to N. ByPass @ Heritage Point 5,353,917.42 5,353,917.42
Details
1
2
2.7
I-75 and SR3/US41/Rocky Face 14,330,999.52 66,015.00
Details
2
3
3.1
Airport Road-Walnut Ave. to S Dalton Bypass 1,343,305.15 943,305.15
Details
3
4
3.11
Veterans Dr. Extension (Flemming Street Reconst) 2,715,171.19 2,715,171.19
Details
4
5
4.1
Waugh St Bridge-GDOT Rehabilitation Project 200,000.00 0.00
Details
5
6
3.6
Antioch Road/Antioch Dr/Eastbrook Rd/Wagner Dr   2,163,217.05 2,163,217.05
Details
6
7
1.11
Glenwood Ave and MLK Jr Blvd 5,982,024.05 5,982,024.05
Details
7
8
2.4
 Intersection N. Dalton Bypass and Cleveland Hwy 7,535,745.98 414,859.02
Details
8
9
2.1
Old Dixie Hwy and S Dalton Bypass 434,798.65 39,151.75
Details
9
10
2.6
College Drive @ Dug Gap Mtn. Rd.(SR 52/I-75)) 1,338,232.55 510,652.88
Details
10
11
1.6
Mill Creek Road and Crider Road 451,321.60 451,321.60
Details
11
12
1.1
South Dixie Hwy and Crossplains Blvd 592,940.97 592,940.97
Details
12
13
1.2
Intersection of Crossplains Blvd and Old Dixie Hwy 947,650.73 947,650.73
Details
13
14
1.12
Glenwood Ave and E. Morris St. 2,415,204.89 2,415,204.89
Details
14
15
3.2
Underwood Road-N Dalton Bypass to Dawnville Rd 3,055,786.97 2,831,905.01
Details
15
16
1.10
Fields Ave and MLK Jr. Blvd 1,936,670.50 1,936,670.50
Details
16
16
3.8
Veterans Drive Extension 6,496,086.44 6,496,086.44
Details
16
17
2.2
SR 201 (LaFayette Rd) and Mt Vernon Rd/Utility Rd 971,915.33 98,393.73
Details
17
18
2.3
SR 201  and Houston Valley Rd/Old LaFayette Rd 1,258,824.52 99,388.80
Details
18
19
5.3
Reed/New Hope Church/Rauschenberg Rd-Improvement   776,466.64 776,466.64
Details
19
20
3.10
Hill Road-Airport Rd to Eastbrook Rd/Wagner Dr 2,202,442.18 2,202,442.18
Details
20
21
5.5
Cohutta Beaverdale Road(East)-Horizontal Improvement 578,532.45 578,532.45
Details
21
22
5.4
Cohutta Beaverdale Road(West)-Horizontal Improvement 1,531,392.16 1,531,392.16
Details
22
23
7.1
Roadway Resurfacing 13,897,500.00 7,643,625.00
Details
23
24
5.1
Hurricane Road-Horizontal improvements  355,656.68 355,656.68
Details
24
25
1.3
Intersection of Lakeland Road and Callahan Rd 7,419,312.78 7,419,312.78
Details
25
26
7.2
Signal Upgrades 1,543,272.00 1,543,272.00
Details
26
27
6.2
Cleveland Hwy Area Drainage Project 930,030.00 930,030.00
Details
27
28
4.3
Dunagan Road @ East Chickamauga Creek 771,257.60 231,211.52
Details
28
29
4.2
Old Dixie Hwy @ Swamp Creek 75,000.00 75,000.00
Details
29
30
5.8
County/City Wide Roadway Safety Improvements 5,590,450.00 5,590,450.00
Details
30
  5.8B Proposed County Road     Details  
31
6.5
Maple Grove Road Drainage Project 743,364.00 743,364.00
Details
31
32
2.8
I-75 and CR 665/Carbondale - Reconstruction 25,521,000.00 0.00
Details
32
33
6.1
Pentz St Area Drainage Improvement Project 722,000.00 722,000.00
Details
33
34
3.5
Airport Road-S Dalton Bypass to Murray Co Line 4,658,992.28 4,658,992.28
Details
34
35
1.7
Burgess Road and Elton Dr. 402,130.96 402,130.96
Details
35
36
1.8
Burgess Road and Tibbs Bridge Road 393,997.05 393,997.05
Details
36
37
1.9
Tibbs Bridge Road and Keith Mill Road 80,584.55 80,584.55
Details
37
38
3.3
Underwood Street from Glenwood to ByPass 3,120,026.74 3,120,026.74
Details
38
39
2.5
SR 71 (Cleveland Hwy)and Maple Grove Road 162,105.00 0.00
Details
39
40
5.2
SR 52 (Walnut Ave) Signal Improvements 1,368,675.00 0.00
Details
40
41
3.7
SR 201 (Realignment) US 41 1,806,443.46 0.00
Details
41
42
3.9
Murray St/East Morris St-Walnut Ave to Glenwood Ave 9,358,863.90 9,358,863.90
Details
42
43
5.6
I-75 @ SR 52/Walnut Ave-Lighting 210,000.00 0.00
Details
43
44
6.4
Old Grade Road Area Drainage Project 622,582.50 622,582.50
Details
44
45
1.4
South Dixie Hwy & W. Ind Blvd/Lucille Dr 676,092.26 676,092.26
Details
45
46
1.5
South Dixie Hwy and Foster Rd.  453,208.96 453,208.96
Details
46
47
5.7
CR 3/Henry Owens Rd. @ NS 719723E 175,000.00 0.00
Details
47
48
6.3
Florence Avenue Area Drainage Project 535,422.00 535,422.00
Details
48
49
5.9
Rauschenburg Road Horizonal Improvement 299,531.85 299,531.85
Details
49
50
4.7
Place Holder for Future Bridge Replacement/Repair Proj 0.00 0.00
Details
50
51
3.13
Place Holder for SR 3(NH-082-1(24)) 0.00 0.00
Details
51
52
7.3
To be named (maybe pvmt marking, shld build, etc) 0.00 0.00
Details
52
53
3.4
Riverbend Road-S Dalton Bypass to Walnut Ave 7,247,058.62 7,247,058.62
Details
53
54
4.4
SR 2 @ Cohutta Creek 0.00 0.00
Details
54
55
4.5
SR 2 @ Conasauga River 511,000.00 0.00
Details
55
56
4.6
SR 3/US 41 @ Little Swamp Creek 50,000.00 0.00
Details
56
57
8.1
ATMS-GDOT Regional TCC-ITS--Construct Center 1,265,000.00 0.00
Details
57
58
2.9
State Route 71 and Wolfe Street 258,709.40 34,558.70
Details
58
TOTAL 155,836,914.53 92,283,681.97